Which two statements are true in this scenario?

You have deployed a load-balancing service for a customer in your Contrail cloud networking environment for their data cache system. Due to the network capacity requirements, the caching servers must be migrated to a different rack of equipment within the data center.

Which two statements are true in this scenario? (Choose two.)
A . A new load-balancing service will be provisioned by the orchestrator prior to moving the caching servers.
B . The orchestration platform can remap the traffic through the existing load-balancing service once the caching servers are moved.
C . The load-balancing service must be decommissioned and re-provisioned once the caching servers are moved.
D . The load-balancing service can be migrated to the vRouters where the caching servers are located.

Answer: B,D

Latest JN0-412 Dumps Valid Version with 65 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments