Which three project permissions does Max need in order to meet these requirements?

For the DEV project, Max has these requirements relating to time logging:

– I need to be able to edit time logs.

– I need to be able to delete time logs.

Which three project permissions does Max need in order to meet these requirements? (Choose three.)
A . Schedule Issues
B . Edit All Worklogs
C . Move Issues
D . Delete All Worklogs
E . Work On Issues
F . Edit All Comments

Answer: BDE

Explanation:

Reference: https://confluence.atlassian.com/jirasoftwarecloud/logging-time-on-issues-902499028.html