Which three factors should you consider before you install an E2860 in a data center? (Choose three)

Which three factors should you consider before you install an E2860 in a data center? (Choose three)
A . current draw
B . electromagnetic interference
C . heat dissipation
D . ambient temperatures
E . fire suppression capacity

Answer: ACD