You need to configure production operations for the pine and orange scent solutions.

Which three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
A . Configure the inventory policy for the item model group to set the value of the Stocked product option to Yes.
B. Use a purchase agreement as a service agreement.
C. Allocate subcontracted work in its own cost breakdown block.
D. Configure a costing resource and requirement to point to a Vendor type resource.
E. Configure the BOM line to be of type Vendor and associate the corresponding vendor account.

Answer: C, D, E