Which strategy minimizes downtime during an upgrade of Cloud Pak for Data platform?

Which strategy minimizes downtime during an upgrade of Cloud Pak for Data platform?
A . Performing the upgrade in-place during peak usage hours.
B . Using a blue-green deployment strategy.
C . Upgrading all nodes simultaneously to speed up the process.
D . Ignoring pre-upgrade checks to save time.

Answer: B