Which stage of the Requirements Engineering process is concerned with tracking requirements from inception to implementation?

Which stage of the Requirements Engineering process is concerned with tracking requirements from inception to implementation?
A . Requirements documentation.
B . Requirements management.
C . Requirements validation.
D . Requirements analysis.

Answer: B