Which section of a performance test script is typically responsible for ensuring the script will have the right values and communication settings during execution?
Which section of a performance test script is typically responsible for ensuring the script will have the right values and communication settings during execution?
A . main section
B . clean-up section
C . initialization section
D . timer section
Answer: B