Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project?
Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project?
A . Architecture Change Management
B . Implementation governance
C . Migration planning
D . Preliminary Phase
E . Requirements Management
Answer: E