Which one of the following is true about Lean Portfolio Management and budgeting?

Which one of the following is true about Lean Portfolio Management and budgeting?
A . It monitors the budgets in the different Agile Release Trains but avoids funding new epics
B. It reviews the top performing solutions to ensure they are staying within budget targets
C. It empowers stakeholders to adapt the current backlog and roadmap context
D. It cannot make any budget changes in the portfolio

Answer: C

Explanation:

This statement is true about Lean Portfolio Management and budgeting that "It empowers stakeholders to adapt the current backlog and roadmap context".

For more details: https://www.scaledagileframework.com/lean-portfolio-management/

Latest SPC Dumps Valid Version with 380 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments