Which of these may a Scrum Team deliver at the end of a Sprint? (Choose the best answer)
Which of these may a Scrum Team deliver at the end of a Sprint? (Choose the best answer)
A . Failing unit tests, to identify acceptance tests for the next Sprint.
B . A single document, if that is what management asked for.
C . An Increment of software with minor known bugs in it.
D . A valuabie, useful Increment that meets the Definition of Done.
Answer: D