Which of the following would BEST be managed with the keep satisfied" stakeholder management strategy?"
Which of the following would BEST be managed with the keep satisfied" stakeholder management strategy?"
A . Those with high power/influence and no interest in the project.
B. Those with high power/influence and some interest in the project.
C. Those with some power/influence and high interest in the project.
D. Those with some power/influence and some interest in the project.
Answer: B