Which of the following would be classified as a weakness in the company’s disaster recovery plan?

After a recent earthquake in a nearby city the board of directors of a company has requested a review of the company s disaster recovery plan.

Which of the following would be classified as a weakness in the company’s disaster recovery plan?
A . Management has decided not to maintain a hot site because it was determined that the costs outweigh the benefits.
B. The details of the disaster recovery plan stipulate that internal audit should review the plan every other year rather than annually.
C. A cold site with backup data and documents is maintained on the basement level of the company s headquarters.
D. Members of the company’s disaster recovery team maintain current copies of the disaster recovery plan m their homes.

Answer: C