Which of the following MOST likely needs to be analyzed before rehosting the ERP?

A company needs to rehost its ERP system to complete a datacenter migration to the public cloud.

The company has already migrated other systems and configured VPN connections.

Which of the following MOST likely needs to be analyzed before rehosting the ERP?
A . Software
B . Licensing
C . Right-sizing
D . The network

Answer: D

Explanation:

The network is the set of devices, connections, protocols, and configurations that enable communication and data transfer between different systems and applications. The network can affect the rehosting of an ERP system to complete a datacenter migration to the public cloud, as it can influence factors such as bandwidth, latency, availability, security, and compatibility. The network needs to be analyzed before rehosting the ERP system to ensure that the network requirements and specifications are met, the network performance and reliability are maintained or improved, and the network security and integrity are preserved or enhanced.

Reference: CompTIA Cloud+ Certification Exam Objectives, page 18, section 3.5

Latest CV0-003 Dumps Valid Version with 144 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments