Which of the following is true for the Backlog Refinement Session?
Which of the following is true for the Backlog Refinement Session?
A . Most of the focus is on the next Iteration, but it allows time to discuss future Iterations and even Features for the next Pl
B. Provides enough time to identify and resolve dependencies and issues that could impact the next Iteration
C. Helps the team think about new Stories prior to Iteration Planning
D. All of the above
Answer: D