Which of the following is NOT required when performing weekly or monthly schedule updates?
Which of the following is NOT required when performing weekly or monthly schedule updates?
A . Percent complete.
B . Remaining duration of activities.
C . Actual finish of activities.
D . Original duration of activities.
Answer: D