What is a key first step in developing a critical path method schedule?

What is a key first step in developing a critical path method schedule?A . Drawing a bar chart of the key phrases of the work.B . Defining the execution plan to meet the required scope of work.C . Setting out the resource to be used and its limitations.D . Drawing...

April 23, 2025 No Comments READ MORE +

At a minimum, periodic reporting must be done at what interval?

At a minimum, periodic reporting must be done at what interval?A . Monthly.B . As requested by the project manager.C . As requested by the owner.D . As specified in the contract documents.View AnswerAnswer: D

April 22, 2025 No Comments READ MORE +

Which of the following is NOT required when performing weekly or monthly schedule updates?

Which of the following is NOT required when performing weekly or monthly schedule updates?A . Percent complete.B . Remaining duration of activities.C . Actual finish of activities.D . Original duration of activities.View AnswerAnswer: D

April 18, 2025 No Comments READ MORE +

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):A . The delay must affect the critical path.B . The delay must be concurrent with the delay attributable to both parties.C . The delay must not...

April 18, 2025 No Comments READ MORE +

What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the...

April 7, 2025 No Comments READ MORE +

Free float is the

Free float is theA . Difference between the early dates and late dates of an activity.B . Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.C . Difference between the early finish dates and late finish dates of...

April 6, 2025 No Comments READ MORE +

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.A . The project plans and...

April 6, 2025 No Comments READ MORE +

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?A . Non-excusable delayB . Compensable delayC . Non-compensable delayD . Excusable delayView AnswerAnswer: A

April 5, 2025 No Comments READ MORE +

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by usingA . Finish-no-earlier constraint on the first activityB . Finish-no-earlier constraint on the last activityC . Finish-no-later constraint on the last activityD . Start-no-later constraint on the...

March 16, 2025 No Comments READ MORE +

What method offers the best chance of the schedule being used effectively to implement the project in the field?

What method offers the best chance of the schedule being used effectively to implement the project in the field?A . Issue detailed schedule updates as frequently as possible.B . Obtain consent and agreement to the schedule from the key project personnel.C . Include detailed and stringent set of scheduling specifications...

March 14, 2025 No Comments READ MORE +