Which of the following is an example of the test closure activity indicated as "lessons learned"?

Which of the following is an example of the test closure activity indicated as "lessons learned"?

K2 1 credit
A . Archive all the test results of the acceptance testing phase
B . Deliver a list of the open defects of a software product released into production to the service desk team
C . Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
D . Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing

Answer: C