Which of the following is a project planning methodology that involves a complex series of required simulations to provide information about schedule risk?

CORRECT TEXT

Which of the following is a project planning methodology that involves a complex series of required simulations to provide information about schedule risk?
A . Monte Carlo Analysis.
B. Project Management Information System (PMIS).
C. Earned Value Management (EVM).
D. Integrated Project Plan

Answer: A