Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor’s baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor’s baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
A . The project plans and specifications
B . The project geotechnical report
C . The regulations published by the government aviation agency
D . The government’s report on future high-clearance bridge projects

Answer: C