Which of the following are likely indicators of ineffective change management?
Which of the following are likely indicators of ineffective change management?
1) IT management is unable to predict how a change will impact interdependent systems or business processes.
2) There have been significant increases in trouble calls or in support hours logged by programmers.
3) There is a lack of turnover in the systems support and business analyst development groups.
4) Emergency changes that bypass the normal control process frequently are deemed necessary.
A . 1 and 3 only
B . 2 and 4 only
C . 1, 2, and 4 only
D . 1, 2, 3, and 4
Answer: C