Which is NOT a key element of stakeholder consultation?

Which is NOT a key element of stakeholder consultation?
A . Ensuring that all major stakeholders for the project have been identified and engaged
B . Ensuring that the same stakeholder representatives are involved throughout the project
C . Ensuring that stakeholders are provided with timely, specific and clear information regarding proposals and their impacts throughout the development process
D . Ensuring that regular feedback on progress is given

Answer: B