Exam4Training

Which ADM phase starts with the receipt of a Request for Architecture Work from the sponsoring organization?

Which ADM phase starts with the receipt of a Request for Architecture Work from the sponsoring organization?
A . Phase A
B . Phase B
C . Phase H
D . Preliminary Phase
E . Requirements Management

Answer: A

Latest OG0-093 Dumps Valid Version with 356 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version