Which activities does the consultant do before the first Fit-to-Standard workshop? Note: There are 2 correct answers to this question.

Which activities does the consultant do before the first Fit-to-Standard workshop? Note: There are 2 correct answers to this question.
A . Evaluate the Business-Driven Configuration Questionnaire responses.
B. Review the integration requirements collected from the Digital Discovery Assessment
C. Deactivate scope items that are NOT part of the Statement of Work/Digital Discovery Assessment.
D. Upload customer master data in the Starter system using migration templates.

Answer: A,B