When the Developers determine that they will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (choose the best answer)
When the Developers determine that they will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (choose the best answer)
A . The Product Owner and all stakeholders.
B . The Scrum Master and the Developers.
C . The Scrum Master, project manager and the Developers
D . The Product Owner and the Developers.
Answer: D