When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner? Please choose the correct answer.

When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner? Please choose the correct answer.
A . During the daily SCRUM meeting
B . During the sprint retrospective
C . During the sprint review
D . During user acceptance testing

Answer: C