When applying WSJF technique, which of the following is considered as a good proxy for project duration

When applying WSJF technique, which of the following is considered as a good proxy for project duration
A . The Job Size
B. The Cost of Delay
C. The Time Criticality
D. The WIP limit
E. The user Business value

Answer: A

Explanation:

https://www.scaledagileframework.com/wsjf/