When a Belt applies the practice of Poka-Yoke to a project challenge she is attempting to make certain the activity is _______________ .

When a Belt applies the practice of Poka-Yoke to a project challenge she is attempting to make certain the activity is _______________ .
A . Well documented
B . Removed from the line
C . Mistake proofed
D . Highly visible

Answer: C