What should you use?

A manufacturer of a bill of materials (BOM) part that is used in multiple products goes out of business.

The part needs to be replaced with a similar part from a different vendor.

You need to identify the products that are impacted to calculate the new cost of the part.

What should you use? Select only one answer.
A . BOM calculations group
B . Where-used report
C . In process production costing report
D . Calculation details for cost and price report
E . BOM version

Answer: B

Latest MB-330 Dumps Valid Version with 198 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments