What should you do?
A company uses Dynamics 365 for Finance and Operations for Process manufacturing. You are reviewing the planned production orders for the next two weeks. There are several
production orders for the same product One order is scheduled to run the week after another order. You need to optimize the planned production orders.
What should you do?
A . Rerun master planning. Select the static plan with a coverage time fence of two weeks.
B . Firm the orders.
C . In Planned orders, combine the production orders.
D . Rerun master planning. Select the dynamic plan with a coverage time fence of two weeks.
Answer: A