What are two possible ways to achieve this goal?

A customer produces light projection toys for holiday decorations throughout the year. You are in the first month of a season. Production flows take one day to complete. The floor supervisor reports that seasonal production targets will not be met. You review the

Kanban schedule board and identify thousands of unplanned jobs. You need to plan the jobs to be completed two weeks prior to the start of the next season.

What are two possible ways to achieve this goal? Each correct answer presents a complete

solution. NOTE: Each correct selection is worth one point.
A . Set the Automatic planning option for each unscheduled job to Yes.
B . Manually schedule each unscheduled job on its due date.
C . Set the Automatic planning option for each unscheduled job to No.
D . Manually schedule each unscheduled job forward from the date of the end of the season.
E . Manually schedule each unscheduled job to the next period of the start of the next season.

Answer: D,E

Latest MB-320 Dumps Valid Version with 141 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments