What should the project manager do to ensure the project is completed on time with quality?

A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.

What should the project manager do to ensure the project is completed on time with quality?
A . Encourage the team to participate in a peer evaluation activity by the end of the project.
B. Introduce the use of time sheets and ask team members to review and submit them regularly.
C. Arrange regular team meetings for the team to update one another on the progress of their assigned tasks.
D. Meet with the team together and in one-on-one meetings to set clear, shared targets.

Answer: D