What project document(s) would determine responsibility?
On a construction project awarded through a competitive process, the electrical contractor says that the AV company is responsible for the installation of conduit.
What project document(s) would determine responsibility?
A . estimate
B . submittals
C . proposal cover letter
D . bid (tender) documents
Answer: D
Explanation:
The responsibility for the installation of conduit in a construction project is typically outlined in the bid (tender) documents. These documents detail the scope of work, responsibilities, and specifications agreed upon during the competitive bidding process. They serve as a binding agreement between the parties and clearly delineate who is responsible for various aspects of the project, including the installation of conduit.
Latest CTS Practice Questions with 193 Q&As
Updated Study Material | Instant Download | Detailed Answers and Explanations