What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier?

Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once.

What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier? Note: There are 2 correct answers to this question.
A . Assign a rounding profile in the material master record of the planned material.
B. Assign the indicator for quota splitting to the lot-sizing procedure being used.
C. Set a maximum quota quantity in the quota arrangement item for each supplier.
D. Set a maximum lot size in the quota arrangement item and activate the 1x checkbox.

Answer: C,D