What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
A . Use the progressed portion of the critical path of all the updates previous to the current update.
B . Use the progressed portion of the critical path of the baseline schedule.
C . Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
D . Use the forward-looking critical path of the most current updates.
Answer: B
Latest AACE-PSP Dumps Valid Version with 120 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments