What is the protocol for recording the results’?

A VxRail Test Plan has been completed

What is the protocol for recording the results’?
A . With the implementation team, complete and document each test, test date, and a screenshot of results
B . In front of a customer, complete each test and document the test date
C . With the implementation team, complete each test and document the test date
D . In front of a customer, complete and document each test, test date, and a screenshot of results

Answer: A

Latest DES-6322 Dumps Valid Version with 60 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments