What is the primary measurement during Inspect and Adapt?

What is the primary measurement during Inspect and Adapt?
A . Program predictability measure
B . Team NPS score
C . Number of Features delivered
D . Number of automated tests

Answer: A

Explanation:

The primary measurement during the Inspect and Adapt (I&A) event in SAFe is the program predictability measure. This metric assesses the Agile Release Train’s (ART) ability to deliver on its commitments within a Program Increment (PI). It helps teams understand how accurately they can plan and execute work, providing a basis for continuous improvement. By focusing on predictability, organizations can improve their planning processes, align better with business objectives, and ensure more reliable delivery of value.

Latest SAFe SASM Practice Questions with 60 Q&As

Updated Study Material | Instant Download | Detailed Answers and Explanations

Subscribe
Notify of
guest
0 Comments