What is the next action for improvement items identified during the Iteration Retrospective?

What is the next action for improvement items identified during the Iteration Retrospective?
A . They are entered as Stories in the Team Backlog
B . They are ROAMed with the rest of the risks
C . They are given to the Scrum Master/Team Coach who resolves them
D . They are escalated to the Business Owners

Answer: A

Explanation:

The next action for improvement items identified during the Iteration Retrospective is to enter them as Stories in the Team Backlog. By adding these improvement items as Stories, they become part of the team’s ongoing work and are prioritized alongside other tasks and user stories for future iterations or sprints1. This way, the team can track and implement the improvement actions and measure their impact on the team’s performance and quality2.

References:

• Iteration Retrospective – Scaled Agile Framework

• What happens to improvement items identified during the Iteration Retrospective? – Service Centre List