What is the most important risk in determining the validity of construction delay claims?
What is the most important risk in determining the validity of construction delay claims?
A . Contractor claims may be submitted prior to completion of the work.
B . Contractor claims may include costs considered in the fixed-price portion of the work.
C . Contractor claims may include subcontractor estimates of balances due to the subcontractor.
D . Contractor claims may be understated.
Answer: B