What is the correct task status flow for a Review task?

What is the correct task status flow for a Review task?
A . Not started -> Reviewed -> Complete
B . Not started -> In Review -> Complete
C . Not started -> In Review -> Reviewed
D . Not started -> In Process -> Reviewed

Answer: C

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments