What is the correct order of the SAP Activate Methodology phases?
What is the correct order of the SAP Activate Methodology phases?
A . Prepare -> Discover -> Explore -> Realize -> Deploy -> Run
B . Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
C . Plan -> Build -> Run -> Sustain
D . Plan -> Design -> Build -> Operate
Answer: B