What is the correct entry for the Fraction Quantity, Start Date, and End Date?

You want to import a leave request for a quarter-day absence on March 23, 2022.

What is the correct entry for the Fraction Quantity, Start Date, and End Date?
A . Fraction Quantity = 0.25, Start Date = March 23, 2022, End Date = March 23, 2022
B. Fraction Quantity = 0.75, Start Date = March 23, 2022, End Date = March, 23 2022
C. Fraction Quantity = 0.25, Start Date = March 23, 2022, End Date = March 24, 2022
D. Fraction Quantity = 0.75, Start Date = March 23, 2022, End Date = March 24, 2022

Answer: A