What is a key first step in developing a critical path method schedule?
What is a key first step in developing a critical path method schedule?
A . Drawing a bar chart of the key phrases of the work.
B . Defining the execution plan to meet the required scope of work.
C . Setting out the resource to be used and its limitations.
D . Drawing the logic diagram.
Answer: D