What happens if the Scrum Team cannot complete its work by the end of the Sprint? (Choose the best answer)
What happens if the Scrum Team cannot complete its work by the end of the Sprint? (Choose the best answer)
A . The Sprints extended temporarily. Lessons are taken to ensure it does not happen again
B . The Sprint is extended and future Sprints use this new duration.
C . The Sprint length is unchanged and the Scrum Team continuously leans and adapts.
Answer: C
Latest PSPO-I Dumps Valid Version with 481 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments
                 
	