What do you have to consider in this scenario?

You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.

What do you have to consider in this scenario?
A . Requirements planning considers only changes that are relevant for scheduling within the planning time fence.
B . Planned orders are created within the planning time fence and automatically firmed by requirements planning.
C . The MRP controller cannot create planned orders within the planning time fence.
D . Planned orders that are created by requirements planning are shifted to the end of the planning time fence.

Answer: D