To integrate the content of an existing Enterprise Content Management system with an IBM Business Process Management solution, where is the initial folder structure of a process instance defined?
To integrate the content of an existing Enterprise Content Management system with an IBM Business Process Management solution, where is the initial folder structure of a process instance defined?
A . Coach settings
B . Process Inspector settings
C . Folder Management settings
D . Process Application folder settings
Answer: D
Explanation:
Reference: http://www.ibm.com/support/knowledgecenter/SSFPJS_8.5.7/com.ibm.wbpm.wle.editor.doc/ topics/rbpmmanagedecm.html (Management of folders and documents with the IBM BPM managed store and an external ECM system)