This shows that the team values which of the following things highest?

A team discovers that their accomplished deliverables are not impacting the goal strongly. They have several more iterations of similar work scheduled and are ready to execute, and they expect delivering this work will produce similar poor impacts. They choose to shift their delivery work to a different initiative while they assess the poorly performing work for other ways that would produce good results.

This shows that the team values which of the following things highest?
A . Documenting solution outcomes
B . Developing new processes
C . Improving collaboration
D . Responding to change

Answer: B