The team’s draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)

The team’s draft plan review consists of which three items at the end of the first day of the Program Increment (PI) Planning event? (Choose three.)
A . Capacity and load estimates (Correct)
B . Program delivery schedule
C . Draft PI Objectives
D . Risks and impediments
E . Iteration Goals
F . Refined team backlogs

Answer: A,C,D