What is the first thing that a team should do to estimate user stories for a project?

What is the first thing that a team should do to estimate user stories for a project?A . Sort the user stories according to priority.B . Schedule a team meeting to understand them.C . Define the story points measure.D . Estimate through function point analysis.View AnswerAnswer: C

September 21, 2020 No Comments READ MORE +

Which is the best option to improve project velocity?

Which is the best option to improve project velocity?A . Shield programmers from interruptionsB . Minimize customer involvementC . Shorten the iteration lengthD . Increase project team sizeView AnswerAnswer: C

September 21, 2020 No Comments READ MORE +

What is a high-level representation of the features or themes that are to be delivered in each release?

What is a high-level representation of the features or themes that are to be delivered in each release?A . Release planB . Product roadmapC . Iteration planD . Product BacklogView AnswerAnswer: B

September 21, 2020 No Comments READ MORE +

In the Lean process, the focus is on:

In the Lean process, the focus is on:A . Managing team efficiency.B . Optimizing completed work across the process stream.C . Using the optimal resources.D . Cross training the team to eliminate bottlenecks.View AnswerAnswer: B

September 21, 2020 No Comments READ MORE +

Applying the Pareto rule when prioritizing the Product Backlog means that:

Applying the Pareto rule when prioritizing the Product Backlog means that:A . features that are lower priority are more likely to slip to the next iteration.B . the value of a feature is not realized until the feature is complete.C . more recent requests are usually more important to the...

September 21, 2020 No Comments READ MORE +

The team estimation game method mainly consists of a:

The team estimation game method mainly consists of a:A . Pile of cards with user, capability, and value to be prioritized by the project team.B . Spreadsheet with backlog issues to be prioritized and each to be given a prioritization number.C . White board session where iterations are estimated and...

September 21, 2020 No Comments READ MORE +

Who is responsible for prioritizing the stories that will be included in the iteration?

Who is responsible for prioritizing the stories that will be included in the iteration?A . ScrumMasterB . DeveloperC . Product OwnerD . TeamView AnswerAnswer: C

September 21, 2020 No Comments READ MORE +

Test-Driven Development (TDD) is a rapid cycle of:

Test-Driven Development (TDD) is a rapid cycle of:A . Requirements, coding, and testing.B . Testing, coding, and refactoring.C . Testing, refactoring, and validation.D . Requirements, coding, and refactoring.View AnswerAnswer: B

September 21, 2020 No Comments READ MORE +

The cost estimation techniques used on Agile projects are:

The cost estimation techniques used on Agile projects are:A . Rule of thumbB . Bottom-upC . ParametricD . Top-downView AnswerAnswer: D

September 20, 2020 No Comments READ MORE +

A company is starting to introduce Agile practices, and the project manager has been asked to identify how to introduce the new process. The project manager’s initial plan should be to:

A company is starting to introduce Agile practices, and the project manager has been asked to identify how to introduce the new process. The project manager’s initial plan should be to:A . Institute daily standup meetings immediately.B . Communicate the Agile Manifesto to the team.C . Balance teaching principles with...

September 20, 2020 No Comments READ MORE +