Acceptance tests of user stories are specified by the:

Acceptance tests of user stories are specified by the:A . Customer at the start of the iteration.B . Customer as late as possible during the iteration.C . Tester after the team has finished the coding.D . Development team at the start of the iteration.View AnswerAnswer: A

September 24, 2020 No Comments READ MORE +

Which best describes the attributes of the IN VEST criteria in a user story?

Which best describes the attributes of the IN VEST criteria in a user story?A . Incremental, Net, Variation, Exceed, Scope, and TrainingB . Interdependent, Nonfunctional, Value, Exploratory, Sprint, and TimeboxC . Innovation, Nested, Vision, Estimating, Scalable, and TeamD . Independent, Negotiable, Valuable, Estimable, Small, and TestableView AnswerAnswer: D

September 24, 2020 No Comments READ MORE +

On what should Agile estimates be based?

On what should Agile estimates be based?A . A Work Breakdown Structure (WBS) from each iteration aligned with the project management planB . A disciplined iteration schedule, which improves predictability, combined with reaction to changesC . Ball park figures collected from past Agile projects with scopes similar to the current...

September 23, 2020 No Comments READ MORE +

In eXtreme Programming (XP), analysis, design, coding, and testing phases are done:

In eXtreme Programming (XP), analysis, design, coding, and testing phases are done:A . At the beginning of the iteration.B . Every day.C . In sequence.D . Without documentation.View AnswerAnswer: B

September 23, 2020 No Comments READ MORE +

Which of the following is a list of valid Agile project planning practices?

Which of the following is a list of valid Agile project planning practices?A . Release planning, Iteration planning, and EstimationB . Estimation, Spike Solutions, and Iteration planningC . Iteration planning, Continuous Integration, and EstimationD . Vision, Release planning, and Performance OptimizationView AnswerAnswer: A

September 23, 2020 No Comments READ MORE +

Which of the following is a list of capabilities, features, and stories that the Product Owner has identified?

Which of the following is a list of capabilities, features, and stories that the Product Owner has identified?A . Burndown chartB . Story cardC . Vision documentD . BacklogView AnswerAnswer: D

September 23, 2020 No Comments READ MORE +

In Agile risk management, a risk burndown chart is best used to:

In Agile risk management, a risk burndown chart is best used to:A . Qualitatively analyze the probability of a risk occurring.B . Track progress on risk reduction of technical risks.C . Document the external risks that could impact the project.D . Illustrate the project risk profile and new and changing...

September 23, 2020 No Comments READ MORE +

The best description of the purpose of the daily standup in Agile projects is to:

The best description of the purpose of the daily standup in Agile projects is to:A . Resolve the key issues and risks that are likely to hinder project progress.B . Provide insight and reassurance to the Product Owner to strengthen that relationship.C . Inform the project lead of project status...

September 22, 2020 No Comments READ MORE +

Agile communication is effective because:

Agile communication is effective because:A . release and iteration planning keep team members aligned, daily synchronization eliminates confusion, and iteration demonstrations keep the team focused on deliverables.B . Agile communication methods focus on detailed, written requirements and specifications that are more complete and allow the team to manage change more...

September 21, 2020 No Comments READ MORE +

User stories are temporary artifacts.

User stories are temporary artifacts. They are considered relevant until the:A . Team completes them.B . End of the project.C . Release is complete.D . End of the sprint.View AnswerAnswer: A

September 21, 2020 No Comments READ MORE +