What should the program manager do?

The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?A . Contact the project sponsors to present the details, impacts, and possible corrective actions regarding the negative cost variance.B . Gather all the details,...

June 27, 2021 No Comments READ MORE +

What should you do next in regard to the vendor's invoice?

You are the program manager for your organization that utilizes vendors from several different organizations. A vendor has submitted an invoice for the work they have completed in your program. You have reviewed the work results and agree with the vendor that their contractual obligation is complete. What should you...

June 27, 2021 No Comments READ MORE +

What is a critical component of the Program Schedule Management Process?

A program in a matrix organization includes subprojects for specific required technologies . The program manager assembles a team of project managers to lead each of the component projects. Each component project requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages...

June 27, 2021 No Comments READ MORE +

What is the program manager’s next step?

A company is releasing a new product geared toward a specific geographic area . The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained. What is the program manager’s next step?A ....

June 26, 2021 No Comments READ MORE +

To ensure continued funding for the program, what should the program manager do next?

An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts, the program manager discovers the program may be shut down due to lack of funding. To ensure continued funding for the...

June 26, 2021 No Comments READ MORE +

What should the program manager do?

To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component . The program manager is concerned that the delivery of some program goals could be jeopardized. What should the program manager do?A . Document the...

June 26, 2021 No Comments READ MORE +

What is this meeting called?

You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any questions the vendors may have about the project. What is this meeting called?A ....

June 26, 2021 No Comments READ MORE +

What should the program manager update first?

A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals. A materials supplier informs the program manager that when this agreement is finalized, it will shorten the product’s...

June 26, 2021 No Comments READ MORE +

What action should the program manager take first?

A program with objectives that impact a large segment of the population receives negative commentary from organizations representing the public interest. What action should the program manager take first?A . Rework the stakeholder engagement plan to foster better relationships with the affected stakeholder groups.B . Review the stakeholder register to...

June 26, 2021 No Comments READ MORE +

Which is the only technique (or tool) available in the Close Project or Phase process?

You are the project manager of a construction project. You have to close a phase of the project. Which is the only technique (or tool) available in the Close Project or Phase process?A . Change control meetingsB . Project management information systemC . Expert judgmentD . ObservationsView AnswerAnswer: B

June 26, 2021 No Comments READ MORE +